Our Articles...
|
www.ame.orgHome Town Kaizen Blitzing Adventures of the "Tranformers," "Tank Tops," and the "Rubberneckers."
Sherrie Ford, Ph.D. Principal, Change Partners, LLC
Target Volume 15, Number 4, Fourth Quarter 1999
In April 1999, two factories in Athens, GA agreed to participate in an AME Kaizen BlitzSM workshop: ABB Power T&D and Oliver Rubber. Both plants have a history of using this tool, but neither had exhausted the possibilities, or have yet to make ti fully a way of life. This was an opportunity to take it to a higher level, plus create a "home town" event. The workshop brought in team members from neighboring plants and organization in Georgia: Noramco (a Johnson & Johnson pharmaceutical company), BellSouth, and Caradon Indalex – with a few from beyond Georgia borders, including Wide-Lite Corporation form Texas and Lexington Furniture Industries from North Carolina.
A Few Unplanned Lessons
Three kaizen teams formed quickly: two at ABB, naming
themselves the "Transformers" and the "Tank Tops," and
one at Oliver Rubber, naming themselves the "Rubberneckers."
All three teams reported on the closing day that by far
their greatest learning had to do as much with the teaming
side of the blitzing as with the takt-timing side. Despite
many weeks of advance planning, more than casual experience
with kaizen blitz as a tool, and well-written mandates
for quantum leaps in productivity, all three teams panicked
when they had not gelled as well-oiled machines by the
end of the education and first day's work.
Similar to the real world, when employees are thrown into
a suddenly-accelerated environment with unclear roles,
an excess of urgency, and no time to sort through everything,
workshop participants at first were looking for someone
to blame for poor organization and planning! "You mean
we've paid good money to learn chaos!?" "you mean I've
taken four days away from my job for this?"
Kaizen Blitz Goals Tackled and Achieved
Well, what did the Transformers, Tank Tops and Rubberneckers
tackle? Did they achieve the goals of the mandate? Let's
take them one at a time:
ABB Power T&D Tank Storage: The Tank Tops
The problem: as in so many plants over 30 years old with
generations of batch manufacturing behind them, this corner
of the plant was a dark world of production leftovers
("Don't now where to put 'em"). Or, "They're ready too
soon for final assembly – gotta put 'em somewhere."
Tanks of all diameters – 13-, 15-, 17- and 20-inch
and odd-ball singletons stacked randomly and anonymously
loomed in their vast storage halls, to the team, like
ghosts. Only one tank per pallet was labeled with the
correct style number. No system existed for locating tanks
in inventory, and housekeeping was unacceptable by the
5S standards. The plant is not yet fully synchronized
to run with the demands of internal customers as the Tank
Tops learned to call takt time, but getting these thanks
in the right place would get them closer to that goal.
The Kaizen blitz mandate: Reduce floor space required;
decrease WIP by 50 percent; cut leadtime by 50 percent;
and improve housekeeping by 25%. Starting at the end of
paint, and ending at tanking, the team scrutinized all
tanks.
Their achievements: all tanks were sorted by diameter
and designated to general areas, resulting in 500 slow-moving
or obsolete tanks being removed altogether. Housekeeping
improved by 30 percent. A clear path for 50 percent reduction
in inventory and leadtime is in place, thanks to the team
efforts; among their suggested additional improvements
were an all-out culture change regarding batch manufacturing,
moving more aggressively to pull systems.
ABB Power T&D Shell Form Mount: The Transformers
The problem: a classic blitz event opportunity! This area
is an assembly line where operators perform on task and
"send it on down the line." The process was burdened by
work flow constraints at the process beginning, with the
operator literally walking miles to get units through
various stages, distributing product and parts into the
plant from time to time. During this walk time, the other
operators waited, up to 25 percent of the total process
time, for their particular operation to be called upon.
The correct tools for operators were not present at the
"point of need" and when they were present, they were
not functioning properly at all times. Preventive maintenance
did not exist in this area.
The kaizen blitz mandate: reduce WIP by 50 percent; shorten
cycle time by 50 percent, increase throughput by 25 percent,
improve housekeeping by 25 percent.
The blitz team started at a banding station addressing
all product through that station. Their achievements included
establishing a kitting approach, allowing a larger number
of necessary parts and materials to travel with the unit
so as to be ready when needed. The Transformers recommended
that the area become cellular, and demonstrated in time
trials the significant increase in throughput that would
result. 5S was a key benefit in light of the many changes
made to processes: the original score of 2.2 out of a
possible 5 was improved to a 3.5 during the workshop,
with more improvements projected. Additional detail about
their achievements is shown in Figure 1.
ABB Power T&D Shell Form Mount: The Transformers’ Achievements |
| Measurement |
Start of Kaizen Blitz |
Results of Kaizen Blitz |
% Improvement |
| Inventory WIP |
|
|
16 % |
| Walking distance (feet) |
8756 |
4400 |
50 % |
| Cycle time (minutes) |
|
|
25 % |
| Productivity (units / person – hour) |
4.1 |
5.1 |
25 % |
| 5Ss (scale 1 to 5) |
2.2 |
3.5 |
59 % |
Figure 1.
Oliver Rubber Splicing the Tread Rework: The Rubberneckers
Until breakthroughs occur upstream in the production of
retreads (which would involve invention of radically different
stacked molds pouring and curing technology), the tread
rework process is critical. This area of the factory was
ripe for blitzing for several reasons. It was the only
area that had not been blitzed before, and it is responsible
not only for the recovery of treads from its own factory
but also for defective treads produced at a sister plant
half a day's drive away.
The problem: this area had 2215 rolls of backlog of unrepaired,
unspliced defective treads. The operators responsible
for all splicing had to walk more than one mile each per
day, with excessive bending, lifting, and reaching. Twenty-seven
out of 38 steps in the process did not add value to the
retread, and of the splicing done before the blitz, 11
percent had to be reworked.
The kaizen mandate: reduce the throughput cycle by 50
percent; improve productivity by 25 percent; reduce defects
by 50 percent; reduce by 50 percent the number of feet
material traveled, starting at the defect storage area
and ending at finishing WIP.
Their achievements: Figure 2 reflects critical gains.
What is not reflected is the major ergonomic improvement
derived from relocating and raising the splicing table
and reorienting the curing station relative to the table
in a way that eliminated the need to twist the body in
moving heavy materials from one to the other.
Oliver Rubber Splicing the Tread Re-Work: The Rubberneckers’ Achievements |
| Measurement |
Start of Kaizen Blitz |
Results of Kaizen Blitz |
% Improvement |
| Space – sq. ft. |
2532 |
1205 |
52 % |
| Inventory |
2215 |
554 |
75 % |
| Walking distance (ft.) |
14,056 |
5336 |
62 % |
| Throughput |
45.4 days |
11.3 days |
75 % |
| Quality (measured as first-pass yield) |
88.3 % |
94.1 % |
50 % |
| Productivity (splices / hour) |
4.70 |
5.64 |
20 % |
Figure 2.
Additional Improvement Suggestion
An interesting side story: in the process of analyzing
all non-value-added steps, the question arose as to whether
there were an alternative to using a particular adhesive
in curing the new splice. The one used at the time had
to be trimmed for each use, because they could purchase
it only in specified lengths. Inquiry with R & D at
a sister plant in Paris, TX led to the discovery that
Tuff Rope, an Oliver Rubber product, had been suggested
years ago as a viable option, with the advantage that
one could cut the necessary length the first time, with
no trimming and no scrap. However for unknown reasons,
Tuff Rope had not been adopted. The cost savings from
Tuff Rope usage was calculated to be significant, but
because it could not be implemented within the workshop
time frame, that gain in not shown in Figure 2.
When You Already Blitz, What's Left to Learn in an AME event?
Both plants had been practicing some form of Kaizen Blitz
before this workshop. A muda (Japanese term for waste
– non-value-added efforts such as repair / rejects
and waiting) sheet, dance charts (like a spaghetti diagram,
a line drawing that illustrates the steps in the current
state of a process), and many other synonyms for AME blitzing
methods were in place. To appreciate the true learnings
in this event, take a look at the "before" and "after"
information in Figure 3 and Figure 4.
| ABB Power T & D |
Already Doing Before AME Workshop
- Had done 20 blitz events in the previous 12 months
- Restructured the organization to make Kaizen Blitz a way of life
- Achieved some great results
- Began to meet with increasing resistance
Gained from the AME Workshop
- Saw that more education is needed before an
event so that skills are imparted, rather than
"just doing it"
- Saw how impressive the thinking can be with
outside perspective from those who "do not know
any better"
- Involved union in the process, gained their
support: "things like this get our people what
they need, allow them to make decisions that
help all of us."
- A renewed sense of commitment, once the communication
cleared up
- A customer happened to visit during the AME
event; it piqued his interest and he asked to
sit in on some of the sessions; most impressed,
he asked for more education and information!
|
Figure3.
| Oliver Rubber Company |
Already Doing Before AME Workshop
- They "kaizen," but they
didn't "blitz," they focused
on incremental, steady improvements over time
- The process was mainly driven by management,
less with people empowerment
- No involvement from outside perspectives
Gained from the AME Workshop
- Blitz! Speed was a definite, exhilarating
contrast
- Results from this event far exceeded
those of their typical kaizens
- Significant business results could be
foreseen if improvements are maintained
- The AME education and skills introduced
will last beyond this event
- Beneficial to have outside eyes to see
what is no longer obvious
|
Figure 4.
One outgrowth from this AME Kaizen BlitzSM workshop was
a desire to start an ongoing forum to lead blitz teams
on one another's shop floors. Can it be that we are witnessing
the next evolutionary step in mastering world-class manufacturing
methods – factory blitz teams within minutes' driving
time of one another, attacking waste and complacency in
products totally unrelated to one's own? Athens, GA thinks
so!
© 1999 AME®
For information on reprints, contact: Association for
Manufacturing Excellence
380 West Palatine Road
Wheeling, IL 60090-5863
847/520-3282
www.ame.org
|